knoxville news
knoxville news knoxville advertising entertainment knoxville obituaries rss linkedin twitter facebook contact smoky mountains knoxville legal notices knoxville classifieds travel knoxville sports business lifestyle knoxville daily sun knoxville daily sun lifestyle business knoxville sports travel knoxville classifieds knoxville jobs knoxville legal notices knoxville yellow pages smoky mountains contact facebook twitter linkedin rss entertainment knoxville advertising knoxville daily sun lifestyle business knoxville sports travel knoxville classifieds knoxville jobs knoxville legal notices knoxville yellow pages smoky mountains contact facebook twitter linkedin rss entertainment knoxville advertising
 

EM prepares for demolition in heart of ORNL

building 3026 demolition oak ridge
Crews are manually adding 12,000 square feet of fabric to the trusses to complete the cover for the protective tent at the Building 3026 demolition project at Oak Ridge. Image by UCOR


OAK RIDGE, TN – The Oak Ridge Office of Environmental Management (OREM) and its contractor UCOR are preparing to demolish the remaining structures associated with Building 3026, the former Radioisotope Development Lab.

“This project is a big step for our program because it marks the beginning of the next phase of major cleanup in Oak Ridge,” said Nathan Felosi, ORNL portfolio federal project director for OREM. “Taking down these hot cells will remove a longstanding risk from the central campus area.”

Workers are finalizing the installation of a six-story protective tent to keep nearby research facilities protected while the final two hot cells from Building 3026 are demolished. Hot cells are thick, concrete rooms that are heavily shielded to provide researchers protection from highly radiative material.

Using a 175-ton crane, crews set a foundation of 92 16,000-pound blocks for the protective tent. Workers then began using the crane to erect 20 steel trusses to create the frame. To complete the structure, nearly 12,000 square feet of fabric is being added in two sections.

Building 3026 was originally built in 1945 to support isotope separation and packaging, but it was later used to examine irradiated reactor fuel experiments and components. The outer structure and four of the facility’s hot cells were demolished using funds from the American Recovery and Reinvestment Act of 2009. However, work has continued on the remaining structures.

building 3026 demolition oak ridge
Building 3026 was so severely degraded that the outer structure was demolished more than 10 years ago. Image by UCOR


building 3026 demolition oak ridge
A 175-ton crane is being used to install a six-story protective cover to keep research facilities near Building 3026 safe during demolition. Image by UCOR


Last fall, UCOR completed tasks to eliminate contamination pathways and prepare the remaining structures for demolition. That included pumping and grouting a 47-foot-long underground transfer tunnel formerly used to load radioactive material into the hot cells.

The protective tent will be completed this month, and demolition is scheduled later this year.

As major cleanup is completed at the East Tennessee Technology Park, OREM is transitioning its skilled, experienced workforce to ORNL and the Y-12 National Security Complex to ramp up large-scale cleanup at those sites.

Crews will work across ORNL’s central campus area to deactivate former research reactors and other radioisotope laboratory facilities in preparation for demolition. This work will eliminate hazards across the site and clear land for future research missions.

Published July 19, 2020










knoxville daily sun Knoxville Daily Sun
2020 Image Builders
User Agreement | Privacy Policy