Henley Bridge Update - March 12, 2011
|
Images by John Disque |
With ten weeks into the Henley Bridge project, things are progressing on schedule.
On the north end of the bridge in the Henley/Hill Ave. intersection, utility work with paving was completed on Friday, March 11, 2011. All that is left there is to relocate a fire hydrant which should take place later down the road.
On the south end in the Chapman/Blount intersection, all gas and water relocations with paving should be completed by next Friday, the 18th.
Traffic counts at the various intersections on the detour and alternate routes are complete. Adjustments to the signalization are being made based on these counts and should be completed by Friday, March 18th.
Published March 12, 2011